Project plan template with Gantt chart (Excel) - free download

An Excel template for the project plan as a bar chart: you enter phases, work packages and milestones with start, end and predecessors, the file draws the Gantt chart by day, week, month or quarter and marks dates that do not fit their predecessors. The file needs no macros, and a completed example comes with it. The files are in German.

  • Download the blank template right away, no e-mail address needed
  • Free to use, including at work
What the template looks like filled in - sample project, City of Lindenau

Project plan - Citizen Service Portal (BSP-2026), as of 31/12/2026

Project manager
Dr Anke Berger
Duration
01/05/2026 - 30/06/2027
Status date
31/12/2026
Timescale
Month
WBS code1Task2Type3OwnerStart4EndDuration5Predecessors6Progress7Check8
1ConceptPhaseDr Berger01/05/202631/07/202692ok
1.1Gather department requirementsWork packageDr Berger04/05/202612/06/202640100%ok
1.2Record service catalogue and current processesWork packageCitizen service dept.18/05/202626/06/202640100%ok
1.3Produce functional conceptWork packageDr Berger15/06/202624/07/2026401.1100%ok
1.4M1 Functional concept approvedMilestoneSponsor31/07/202601.2; 1.3100%ok
2Procurement and interfacePhaseDr Berger03/08/202615/03/2027225ok
2.1Tender and awardWork packageDr Berger03/08/202625/09/2026541.4100%ok
2.2M2 Contract awardedMilestoneSponsor30/09/202602.1100%ok
2.3Interface to residents' registerWork packageIT coordination01/10/202605/03/20271562.245%ok
2.4M4 Interface to residents' register acceptedMilestoneIT coordination15/03/202702.30%ok
3Pilot operationPhaseDr Berger03/08/202630/11/2026120ok
3.1Set up portal and configure pilot servicesWork packageVendor01/10/202620/11/2026512.2100%ok
3.2Data protection impact assessmentWork packageIT coordination03/08/202630/11/20261201.470%overdue
3.3Works agreement with the staff councilWork packageDr Berger03/08/202623/10/2026821.4100%ok
3.4Approval of pilot operationQuality gateSteering committee27/11/202603.1; 3.3100%ok
3.5M3 Pilot operation with three servicesMilestoneCitizen service dept.30/11/202603.4100%ok
4Roll-out and handoverPhaseDr Berger11/01/202730/06/2027171ok
4.1Case worker trainingWork packageDr Berger11/01/202726/02/2027473.50%ok
4.2Activate nine further servicesWork packageVendor01/02/202723/04/2027822.4; 3.20%start before predecessor
4.3Handover to regular operationWork packageIT coordination03/05/202725/06/2027544.40%ok
4.4M5 All twelve services onlineMilestoneDr Berger30/04/202704.20%ok
4.5M6 Handover to regular operationMilestoneSponsor30/06/202704.30%ok

Notes on the fields

  1. 1WBS code: Number from the work breakdown structure: 1 for the phase, 1.1 for the first work package in it. The predecessors column refers to these codes, and the check column uses them to tell which tasks belong to a phase.
  2. 2Task: Phases, work packages and milestones from the work breakdown structure; individual tasks do not belong here. A milestone names the result that is accepted, such as "functional concept approved".
  3. 3Type: Phase, work package, milestone or quality gate, the same types as in the WORKSPACE.PM Gantt chart. Phases get a light grey bar, work packages a grey one that fills with blue as progress is made, milestones a diamond and quality gates a triangle.
  4. 4Start: For milestones and quality gates enter the start only. They are points in time and have a duration of 0.
  5. 5Duration: Calculated by the file: calendar days including the end day, as in WORKSPACE.PM. From 04/05 to 12/06 is 40 days. The template does not subtract weekends or public holidays.
  6. 6Predecessors: WBS codes of the tasks that must be finished before this one starts, several separated by semicolons ("3.1; 3.3"). The template checks finish-to-start relations and moves nothing: if a predecessor slips, the check column flags the successor, and you enter the new dates yourself.
  7. 7Progress: Percent complete. The completed share of the bar turns blue. For milestones 100% means reached. For phases the field stays empty.
  8. 8Check: Formula: "start before predecessor" if a predecessor only ends on the start date or later. "phase too short" if a task of the phase lies outside its period. "overdue" if the end is before the status date and progress is below 100%. In the example row 4.2 is red: M4 has slipped to 15/03/2027, while activating the further services is still set to begin on 01/02/2027.

What a project plan with Gantt chart is

Project plan here means the schedule of a project: when each work package starts and ends, what depends on what, and when the milestones are due. As a Gantt chart, also called bar chart, the list of tasks is on the left and a timeline on the right, on which every task runs as a bar from its start to its end. Milestones have no duration and appear as a diamond.

Henry L. Gantt popularised the format in the USA between 1910 and 1915 for controlling production orders. The Polish engineer Karol Adamiecki was already working with a similar "harmonogram" from 1896 but only published it in 1931. In Germany, DIN 69900 describes the schedule list and the bar chart alongside the network diagram.

In the steering committee the plan has to show whether the end date will hold. A bar chart can only show that if the dependencies are in it. That is why the template has a predecessors column and a check column that reports when a task starts before its predecessor is finished. The critical path and float are calculated by a network diagram; a spreadsheet without macros cannot do that.

The template comes as an Excel file and as a PDF for printing, plus the completed sample above from the fictional "Citizen Service Portal" project of the City of Lindenau, as of 31/12/2026. One row in it is deliberately red and one yellow.

How to fill in the project plan

Start with the structure; the dates come later. Take the phases and work packages from the work breakdown structure with their WBS code: 1 for the phase, 1.1 and 1.2 for the work packages in it. Milestones get a code in the phase they close and, in their name, the result that is accepted. If there is no work breakdown structure yet, that is the first step.

Then the sequence: the predecessors column says what must be finished before a task can start. Every task except the first needs a predecessor, every task except the last a successor. A work package with neither is left hanging, and nobody notices when it slips.

Now the dates: estimate the duration of each work package, set start and end and go through the chain from front to back. Leave a buffer before important milestones, especially if you are planning backwards from a fixed end date.

At the top of the sheet you set up the timeline. Timeline from: leave empty to start at the earliest start date. Timescale: day, week, month or quarter; week suits projects up to about six months, month longer ones. Status date: its column is shaded, and the check column counts "overdue" from this date. Without an entry, today's date applies.

After that you enter progress, change dates that have moved and read the check column. Save the first approved version as a separate file; without this baseline nobody can see later how far the dates have moved. In the example row 4.2 is red because M4 has slipped to 15/03/2027 and activating the further services is still meant to begin on 01/02/2027. Row 3.2 is yellow: the data protection impact assessment was due at the end of November and stands at 70%.

Typical mistakes in project plans

Bars without dependencies
Every bar stands on its own, no row has a predecessor. That looks tidy but only shows wishful dates: when a work package slips, nobody can see what depends on it.
Planned in too much detail
Whoever enters every task separately soon has three hundred rows. After two weeks the plan is out of date and nobody maintains it. The work packages from the work breakdown structure are enough; only the next few weeks may be planned in more detail.
Duration confused with effort
Ten person-days of effort take twenty working days if the colleague only works on the project every other day, which is about four weeks with weekends.
No buffer before the milestone
All work packages follow each other to the day, and the milestone is the day after the last one. The first week of sick leave moves the date the sponsor has in the calendar.
Milestones without a result
"End of phase 2" says when something should be over, but not what is finished by then. A milestone names a result that someone accepts, such as "contract awarded" or "interface accepted"; then it is clear whether it has been reached.
Dates overwritten, baseline lost
With every delay the old date is overwritten. The status report then says "on schedule" because the plan is always the latest version. Save the approved version as a copy before you change any dates.

When the Excel template is no longer enough

For a project with twenty to forty tasks planned by one person, the Excel file is enough. It gets difficult when dates move often. The file then reports that successors no longer fit, but does not calculate where they slip to and does not show which chain determines the project end. Every delay adds red rows, and someone has to fix each one by hand.

In WORKSPACE.PM the project plan is the project's Gantt chart, built from the work breakdown structure:

In the fileWORKSPACE.PM
Dependencies are text in a column; the check column only knows finish-to-start relations.Predecessors are typed as WBS codes or dragged between two bars, with all four relation types and lag, for example "6.4EE+3" (finish-to-finish plus three days). Circular references are detected and named.
Which tasks determine the end date and how much float the others have is written nowhere.The network calculation determines earliest and latest start and finish and the total float for every task; the critical path can be highlighted in the Gantt chart.
Phases carry whatever dates someone typed in; the check column only reports when a work package sticks out.Phases always take their period from their work packages and follow every change immediately.
The baseline is a copy of the file; comparing means two windows side by side.Baselines are frozen and shown in the Gantt chart as a second bar below the current plan, with the variance in days.
How a milestone has moved over the months can only be pieced together from old versions.The milestone trend analysis shows the dates of every milestone across the project's reporting dates and classifies them, for example as stable, trending late or reached.

This template exists in WORKSPACE.PM as a Gantt chart per project

The Gantt chart in WORKSPACE.PM shows the project structure on the left with WBS code, duration, start, end, predecessors and owners, and the bars on the right, with a timescale from day to year. Phases, work packages, milestones and quality gates are the same types as in the template, and duration is counted the same way, in calendar days including the end day. On top come the network diagram with the critical path, baselines for comparison, the milestone trend analysis and export to Excel or PDF.

See Gantt chart and scheduling in WORKSPACE.PM

Frequently asked questions about the project plan template

01What does the template cost, and do I have to sign up?

Nothing, and no. The blank templates are directly behind the links, with no form and no email address. Only the completed example is sent by email on request.

02How does the Excel file draw the bars?

With conditional formatting, no macros. Every column of the timeline stands for a day, a week, a month or a quarter, and a cell is coloured when the task falls into that period. A formula places milestones as a diamond in the column of their date. Change start or end and the bar follows immediately.

03Does the template calculate the successors' dates?

No. It only checks: if a task starts before one of its predecessors is finished, the check column says "start before predecessor". You enter the new dates yourself. A network planning tool calculates dates from the dependencies, with float and critical path.

04What is the difference between project plan, bar chart and network diagram?

Project plan is used in two senses: narrowly for the schedule, broadly for all plans of a project, including structure, costs and resources. The bar chart (Gantt chart) shows the tasks as bars on a timeline, easy to read for outsiders too. The network diagram shows the tasks as nodes with their dependencies and calculates earliest and latest dates, float and the critical path. Both are based on the same tasks and dependencies.

05Day, week, month or quarter: which timescale fits?

That depends on the duration: days for undertakings of a few weeks, weeks up to about six months, months for projects of one to two years, quarters for an overview of a programme. The template has a fixed number of columns for this; you switch the timescale at the top of the sheet and the bars adjust.

06How many rows should the plan have, and how do I add more?

As many as there are phases, work packages and milestones in the work breakdown structure, twenty to forty for a mid-sized project. The template has 30 prepared rows, enough for one A4 landscape page. For more, copy an empty row and insert it inside the table with "Insert Copied Cells"; formulas and formatting come along.

07How do I show the plan to the steering committee?

The sheet is set up for A4 landscape, fitted to page width. For the steering committee the level of phases and milestones is often enough: filter the Type column and Excel hides the other rows together with their bars.

08Does the template work in LibreOffice?

The Excel file contains no macros; bars, diamonds and check column are ordinary formulas and conditional formatting. LibreOffice Calc replaces the Calibri font with the metrically identical Carlito, so columns and line breaks stay the same. We have tested the template with Microsoft Office.

09May I adapt the template and use it at work?

Yes, commercially too, in any number of projects, with your own columns and types. Only resale and publication as your own template are excluded.

Maintain the project plan in the project instead of in file versions